These are the key milestones - past and future.
---------------------------------
Past Milestones:
Project Commencement - 23 February
First Meeting - 2 March
Initial POA / Brief finished - 10 March
Sketches Drawn up and shown to client - 18 March
Survey Handed out to customers - 22 March
General Research on Costume hire sites finished - 23 March
Website Code Started - 27 March
Website Version 0.1 finished - 22 April
Survey Collated - June 7
----------------------------------------
Future Milestones:
Website Content all included in site, including galleries (without design being finished) - 22 June
Final Brief Done - 29 June
Hosting research finished - 24 July
Website Finished, final modifications Done - 31 July
Website Handed Over to client - 7 August
Tuesday, June 16, 2009
Subscribe to:
Post Comments (Atom)
This would probably look better in Gantt chart as then the resources can be visable off to one side AND there would be a visual indication of progress over time (hard to get from dates within the text.
ReplyDeleteSome discussion on how you view your progress and the state of the play may be useful. You could give an overview of problems encountered and potential or foreseen dificulties. They like this sort of thing for Merit and Excellence.